From: Jennifer M. <jm...@ps...> - 2008-01-23 15:43:21
|
On Jan 23, 2008, at 10:12 AM, KM wrote: > Doesn't really solve your problem - but one thing we did when using > mantis is to use the project as the version. It helped us look at > things in more organized "sections" so to speak. e.g. MyProj 1.0, > MyProj 1.1, etc. Basically at the end of one version/release/ > project, any open issues are moved to the next one - etc - basic > stuff. > > [...] > > just an idea for organization - but sorry can't help you with the > exact problem. It's a good idea. We already have subprojects (bugs, enhancements, and user-requested enhancements). I hope to eliminate use of the bugs and enhancements subprojects in 1.1 and use categories instead (moving the current categories to tags). We might be able to implement this then. Unfortunately, our vendor sometimes takes several years to fix bugs so we'd need to maintain the category list for all of the version projects. That would still simplify things. Thanks, -J. |