From: Stephen J. <st...@ph...> - 2008-06-13 16:32:13
|
Due to a hardware failure on my old server, I recently set up a new backuppc server and it backs up about 85 hosts with a 60-day FullPeriod. Because I started fresh, right now all of the hosts' schedules are in lock-step (all got a full the first day, an incr level 1 the next, ...) On my old server I had staggered the fulls so that only one or two hosts got a full each night, while the rest got some level of an incremental. This was a pain to get going--logging each each day and doing a manual full of one or two hosts, but worked great to keep the backup window managable once it was going. So my question is has anyone came up with an automated method to stagger the separate hosts' fulls across multiple days? Cheers, Stephen |