I am clicking tasks in the order I want them linked, but the link always goes from the earlier on in the listing to the later. For example, I want task 20 to be the predecessor of task 10, in other words 20 --> 10. So I click task 20, and then task 10, and click Link. But the link goes from 10 --> 20. I could manually enter the predecessor numbers in the predecessor column. But there are dozens of these. A click method would be much better. Any pointers? Thanks, Bill