Hello Tahoeob, Many thanks for the reply. I did what you suggested (Fix duration and No driven by effort) and it seems to work. In all the cases, I need to look at this in detail. I'll update the thread when I confirm the behaviour of the program here, and if necessary, upload the program. Many thanks!
Hello Tahoeob, Many thanks for the reply. I did what you suggested (Fix duration and No driven by effort) and it seems to work. In all the cases, I need to look at this in detail. I'll update the thread when I confirm the behiaviour of the program here. Many thanks!
Hi all, I'm using Project Libre Version 1.9.3, and I finding a problem when perform the assignment of resources to a task. I've created several resources (people in this case) and I want to assing them to a task. When I select them and give to each one a percentage of the total (let say, Person A 70%, Person B 30%). this reflects on the hours for each person, as example, if the task lasts 100 hours, Person A has 70 hours, Person B 30 hours. However, if a change the percentages, or add a third person,...