Menu

Multi-role Tasks

Help
2011-12-27
2013-04-29
  • Giancarlo Susin

    Giancarlo Susin - 2011-12-27

    Hi,

    I'm trying what the xProcess' Help calls "Multi-role Tasks": coarse tasks assigned to different roles, with specific proportions of effort for each role.

    But it seems that, with this kind of task, the scheduler can do weird things in one use case:

    1. the project manager creates a task with 2 roles, 50% of total effort for each role;
    2. one of the project participants confirms some effort done in the task;
    3. the project manager adjusts "Estimate to complete" of each role, reducing time of this participant's role and increasing the other role's time accordingly (in task editor, opening tab "Required Resources").

    At this point the scheduler runs, allocating more time than the task's total estimate to complete and making task to last more than expected.

    This can be confirmed in task editor, tab "Required Resources" (box "Assignments"): the column "Effort Remaining" shows more time than task's "Effort to complete".

    Am I understanding correctly how this kind of task works?

    Thanks in advance.

    • Giancarlo
     
  • Flemming

    Flemming - 2012-01-03

    Hi Giancarlo,

    I was not able to reproduce the "weird things" - I tried to follow your steps and after every save (and scheduler run) the values for "Effort Remaining" and "Effort to complete" were the same. If you let me know more detail of which values you entered where and which values came out as a result I will give it another try.

    Flemming

     
  • Giancarlo Susin

    Giancarlo Susin - 2012-01-03

    Hi Flemming,

    Sorry, I realized that I wasn't clear enough. My use case also includes re-estimating of individual effort to complete by each participant, in a daily meeting. So, at step 3, you have to change estimates more than the amount of time completed until that moment.

    In your example, please change "Estimate to complete" for Role2 from 10 to 4, and for Role1 from 16 to 22 (summing up 26). You'll note that "Effort Remaining" now reads 27.1. As I see it, it should be 26. Follows my screen.

    I appreciate very much your help.

    • Giancarlo

     
  • Flemming

    Flemming - 2012-01-05

    Hi Giancarlo,

    I can not see your screenshot but could reproduce the behaviour following your description. I also now see that although in my screenshot the sum of "Effort Remaining" is correct the way it is split is not. The "Effort Remaining" values for the Roles does not match the corresponding "Estimates to Complete". I assume that there is a calculation error somewhere and will look into it and get back to you.

    Flemming

     
  • Giancarlo Susin

    Giancarlo Susin - 2012-01-06

    Hi Flemming,

    It seems you found the cause of the problem. I'll stay monitoring that bug report. Thank you!

    • Giancarlo
     
  • Andy Carmichael

    Andy Carmichael - 2012-01-12

    See my reply to the tracker… Link above.

     
  • Andy Carmichael

    Andy Carmichael - 2012-01-20

    Fixed in build 3414. Will be released in the next release.

     
  • Andy Carmichael

    Andy Carmichael - 2012-01-28

    Beta (3.6) now available.

     

Log in to post a comment.

MongoDB Logo MongoDB