From: opto <bu...@op...> - 2014-09-24 19:15:40
|
I still fully support what I wrote two years ago: 1) MRP must be for start of WO, not for end of WO. Components must be available when I start manufacturing. 2) It would be preferable to have lead time for components. If they cost 20.000 EUR, I do not want to order them before wo start if I only need them after 12 weeks (optimise flow of capital funds) 3) History of wo changes is required by German and European product laws. I think I provided a bug fix for 1) in 2012. 2) We have lead time for parts I buy. how about defining myself as supplier for those parts I produce, define the item, then I have the field for the lead time and can even use that on my own components. So for all manufactured components, I would either use 0 or the time from: supplier:myself/mycomponent/leadtime Klaus -- View this message in context: http://weberp-accounting.1478800.n4.nabble.com/Bug-MRP-for-WO-at-reqdate-instead-of-startdate-tp4651206p4657670.html Sent from the web-ERP-developers mailing list archive at Nabble.com. |