Menu

Using the PreRequisites

Evanzab
2014-05-07
2026-01-20
  • Evanzab

    Evanzab - 2014-05-07

    Hi,
    I can't seem to figure out how to assign one task to be the prerequisite of another task. How is this done? Also, what happens when you try to 'Start Tracking Effort' on a task that doesn't have its prerequisites fulfilled?
    Thanks!
    -Evan

     
  • Evanzab

    Evanzab - 2014-05-07

    Note - I just found the 'Create new task with selected tasks as prerequisites' ... but that does not seem to work.

     
  • Evanzab

    Evanzab - 2014-05-08

    I figured out that it had the hide inactive tasks filter on, and i hadn't made any active yet.

    It appears there is nothing that prevents making a task active or tracking effort if the prerequisite has not been met. Is there a way to get it to do something like prevent it or pop up a warning that the pre-req has not been met yet?

     
  • Aaron Wolf

    Aaron Wolf - 2026-01-20

    In case still using or want to come back to Task Coach, it's now finally getting updated again but moved to https://github.com/taskcoach/taskcoach

    Cheers

     

Log in to post a comment.

MongoDB Logo MongoDB