When exporting the EFFORT AS CSV, the "option" to split the date and time is indicated for the "Task" but it's still active for the effort, however, the tasks are in the same column, verified in the raw datas. For my tracking purposed, I must be able to export the EFFORT and have Date and Time in 2 separate comma delimmated fields so that Excel will more easily split them properly.
The actual bug is that the "split date and time" option should be disabled when effort is selected. Since it's a date span, that would make 4 columns in total right ?
A fix was made and checked into the source code repository of Task Coach. The fix will be part of the next release. You will get another notification when that release is available with the request to install the new release and confirm that your issue has indeed been fixed.
If you like, you can download a recent build from http://www.fraca7.net/TaskCoach-packages/latest_bugfixes.py to test the fix.
Because a fix has been made for this bug report, the priority of this report has been lowered to 1 and its resolution has been set to 'Fixed'.
Thanks, Task Coach development team
This bug should be fixed in the latest release of Task Coach. Can you please install the latest release of Task Coach and confirm that this bug has indeed been fixed?
Thanks, Task Coach development team