PL1.7.0 - Windows7 - Java8-update111
Hi found some weird behaviour with automatic start date of plain task. in attached project I got some tasks in row 3 to 11which have no contraints an no fixed dates. But PL shows them "starting" at 07.09.2016. Actually I was expected to see them starting at project starting date, which is 22.08.2016.
If I add a plain task just above row 3 --> it is drawn at 07.09.2016. Again I was expected to see it to startat project starting date.
Now the funny part: if I do add a task (anywhere) and directly delete the new line --> then PL recalculates the project and the mentioned tasks from above correctly arrange at project start.
So what went wrong here?
Regards
Ralf
Besides: is there any other proven way to manually recalculate the project other than the above mentioned procedure with adding and deleting a new task?
Diff: