Ralf Mueller - 2017-06-10
  • Description has changed:

Diff:

--- old
+++ new
@@ -1,3 +1,6 @@
+PL1.7.0 - Windows7 - Java8-update111
+
+
 Hi found some weird behaviour with automatic start date of plain task. in attached project I got some tasks in row 3 to 11which have no contraints an no fixed dates. But PL shows them "starting" at 07.09.2016. Actually I was expected to see them starting at project starting date, which is 22.08.2016.

 If I add a plain task just above row 3 --> it is drawn at 07.09.2016. Again I was expected to see it to startat project starting date.
  • Component: Other --> Scheduling