I am clicking tasks in the order I want them linked, but the link always
goes from the earlier on in the listing to the later.
For example, I want task 20 to be the predecessor of task 10, in other
words 20 --> 10. So I click task 20, and then task 10, and click Link.
But the link goes from 10 --> 20.
I could manually enter the predecessor numbers in the predecessor
column. But there are dozens of these. A click method would be much
better. Any pointers?
I am clicking tasks in the order I want them linked, but the link always
goes from the earlier on in the listing to the later.
For example, I want task 20 to be the predecessor of task 10, in other
words 20 --> 10. So I click task 20, and then task 10, and click Link.
But the link goes from 10 --> 20.
I could manually enter the predecessor numbers in the predecessor
column. But there are dozens of these. A click method would be much
better. Any pointers?
Thanks,
Bill