Menu

#388 Original planned time is lost for relaunched overspent in-progress tasks

v2.7
closed-fixed
None
9
2023-09-15
2022-02-08
David Tuma
No

If a task is in progress (i.e., started but not yet marked complete) when a project is relaunched, the relaunch wizard is designed to:

  • copy the task into the new project iteration
  • mark the task complete in the old project iteration
  • adjust the planned times in the old and new iterations, so:
    • the new iteration receives the planned remaining time
    • the total planned time for the task does not change (because the sum of the new and old planned times equals the original planned time)

Unfortunately, the final item above was not working as expected when an in-progress task was overspent (that is, more time had already been spent than planned). In that situation, the total planned time was increasing to match the overspent amount.

Discussion

  • David Tuma

    David Tuma - 2023-05-03
    • Group: Incoming --> Fix Available
     
  • David Tuma

    David Tuma - 2023-09-15
    • status: open --> closed-fixed
    • Group: Fix Available --> v2.7
     
  • David Tuma

    David Tuma - 2023-09-15

    Fixed in Process Dashboard version 2.7

     

Log in to post a comment.