WBS Editor ignores "pruned task" flag
Brought to you by:
ken_raisor,
tuma
The Task & Schedule window allows individuals to "prune" tasks from their earned value plan. When a task has been pruned, it no longer affects earned value calculations. For example, it no longer counts for or against actual progress, and it no longer affects forecast date calculations.
Unfortunately, the WBS Editor does not follow the status of these "pruned task" flags; the WBS views these as tasks that still need attention. As a result:
Fixed in Process Dashboard version 2.6