Stefan Mueller
-
2011-02-18
- priority: 5 --> 9
Once we began using the new feature of Level of Effort Tasks in the Task & Schedule Tool we encountered that the effect of that Tasks is not considered within the WBS. That means that the estimated completion dates are wrong (far too soon) in the WSB.