When I change the working calendar, changes are not made in my calendars, and when I go into the "Change Working Calendar" window, the same "Standard" option is selected. Any new calendar I create is not saved when I close and open openproj again.

Discussion

  • Comment has been marked as spam. 
    Undo

    You can see all pending comments posted by this user  here

    Anonymous - 2012-05-23

    Hi,

    all what you have to do is to check the "Ignore resource time" box, as your calendar and the resource's are conflicting.

    I worked with me :-)

    B,

     
  • Comment has been marked as spam. 
    Undo

    You can see all pending comments posted by this user  here

    Anonymous - 2012-05-23

    Hi,

    all what you have to do is to check the "Ignore resource time" box, as your calendar and the resource's are conflicting.

    I worked with me :-)

    B,

     
    Last edit: Anonymous 2014-02-23
  • Tahoeob

    Tahoeob - 2012-07-23

    Hi Martin, I just posted a note on the pending release of ProjectLibre which will fix the issues you are having. We are hosting ProjectLibre on SourceForge as well. We were the founders and developers of OpenProj and happy to be updating it...............

    * Bug fixes (many, many, many)
    * Microsoft Project Import/Export fixed
    * Printing being added
    * other items

     

Log in to post a comment.

Get latest updates about Open Source Projects, Conferences and News.

Sign up for the SourceForge newsletter:





No, thanks