|
From: Daniele T. <d.t...@ic...> - 2002-03-13 09:06:41
|
Dear Peter, On Tuesday 12 March 2002 15:23, Peter Edwards wrote: > I find there is a problem with dummy activities where multiple threads = are > joined (Join kind 'and'). The activity waits as required until all inco= ming > transitions are signalled, but the dummy activity remains 'inactive'. I > have to manage the workflow to activate and then complete the dummy > activity, then the workflow continues as expected. thank you, bug fixed, cvs updated =3D) Can download cvs version of openflow from: http://sourceforge.net/cvs/?group_id=3D2370 Thanks again, =09Daniele |