MU2 Progress

2015-08-31
2017-01-18
<< < 1 .. 14 15 16 17 18 > >> (Page 16 of 18)
  • fsgl

    fsgl - 2016-05-04

    !الله كريم

    (Allah karim!)

    (God is merciful!)

     
  • Brady Miller

    Brady Miller - 2016-05-05

    Congrats Harley!

    And, yes, the plan is to not proceed with the certification until it is all complete(ie. the next stop will be Full certification). I'll send Milton an email to confirm this.

    -brady
    OpenEMR

     
    • Harley Tuck

      Harley Tuck - 2016-05-05

      Thank you, yes indeedy. It's good to all be on the same page.
      - HT

       
  • Brady Miller

    Brady Miller - 2016-05-05

    Hi ZH Healthcare and Jacob,

    Just let me know when you are ready for next code review on the e2/f2 items. This is a good time to get this done before things gets busy with Visolve's work.

    thanks,
    -brady
    OpenEMR

     
  • Terry Hill

    Terry Hill - 2016-06-04

    Has there been any progress on this and is there a completion date in site?

    Terry

     
  • Tony McCormick

    Tony McCormick - 2016-06-10

    Reminder: Hardship Exception Applications are Due by July 1, 2016 for the Medicare EHR Incentive Program

     
  • Brady Miller

    Brady Miller - 2016-06-11

    Hi,

    Here is code by Visolve to pass the Clinical Quality Measures items. It's already undergone several revisions and it's likely ready to come into the codebase. I plan to bring it into the codebase soon unless anybody has issues with it. The code is here:
    https://github.com/openemr/openemr/pull/138

    thanks,
    -brady
    OpenEMR

     
    • Brady Miller

      Brady Miller - 2016-06-14

      I just committed this code into the main codebase.

      -brady
      OpenEMR

       
  • Tony McCormick

    Tony McCormick - 2016-06-12

    Is this all new code or updates to the code Ensoftek contributed?

     
  • Brady Miller

    Brady Miller - 2016-06-12

    Hi Tony,
    It's updating of the code contributed by Ensoftek along with completion of several unfinished pieces.
    -brady
    OpenEMR

     
  • Brady Miller

    Brady Miller - 2016-06-12

    Hi,

    Here is code by ZH Healthcare to pass the following MU2 items:
    170.314(f)(1) Immunization Information
    170.314(e)(2) Ambulatory setting only - clinical summary

    It's already undergone several revisions and it's likely ready to come into the codebase. I plan to bring it into the codebase soon unless anybody has issues with it. The code is here:
    https://github.com/openemr/openemr/pull/139

    thanks,
    -brady
    OpenEMR

     
    • Brady Miller

      Brady Miller - 2016-06-19

      I just committed above code into the main codebase.

      -brady
      OpenEMR

       
  • Tony McCormick

    Tony McCormick - 2016-08-26

    How's that last piece coming? We have to be certified and on the CMS site by Oc1 1 for anyone to be able to do MU2 this year..

     
    • Stephen Waite

      Stephen Waite - 2016-08-26

      hi Tony, expect good news in 2-3 weeks.

       
  • Brady Miller

    Brady Miller - 2016-08-27

    More detailed update:
    1. Usability testing (item G3) by 3 extremely generous volunteers is happening this weekend. If all goes well, then the report for this last item will be turned in next week.
    2. Turns out item a1 (CPOE) was never tested. It's super simple and plan to get that passed next week.

    So barring any more surprises, should be submitting for MU2 late next week (which can then take several weeks to process). It is going to be very close to the 10/1 deadline...

    -brady
    OEMR Organization

     
  • Brady Miller

    Brady Miller - 2016-08-31

    micro-update:
    1. item G3: The usability testing report has been turned in(thanks to the usability testing volunteers and visolve for working non-stop on this over the weekend).(hopefully the report will be accepted and will hear back soon on this; if so, then this item will be passed)
    2. item a1: CPOE test for cert will be done on 9/1.

    I have confirmed with infogard that the above items are the only items remaining. Thus, if all stars align, we could be submitting for full MU2 cert at the the end of this week (and then there's still a several week turn around time).

    -brady
    OEMR Organization

     
  • Brady Miller

    Brady Miller - 2016-09-02

    micro-update:
    1. item G3: Several modifications were requested by Infogard on the usability testing report. Hopefully will be turning in the revised report tomorrow.
    2. item a1: Visolve passed this item today! Thank you Visolve!

    -brady
    OEMR Organization

     
  • Brady Miller

    Brady Miller - 2016-09-08

    micro-update:
    1. item G3: Passed. Thank you Visolve!

    All items are completed and Infogard is currently verifying everything before sending application to ONC.

    Check out the beautiful, all purple barometer:
    http://www.open-emr.org/wiki/index.php/OpenEMR_Certification_Stage_II_Meaningful_Use#Completion_Barometer

    -brady
    OEMR Organization

     
    • Stephen Waite

      Stephen Waite - 2016-09-08

      Great news! Congratulations!

       
  • Brady Miller

    Brady Miller - 2016-09-12

    micro-update:
    A "technical review" will be performed by Infogard near the end of this week, which takes several days. Once this is complete, the application then goes to ONC and takes 7 business days. So, if all goes well, then plan to release 5.0.0 with complete MU2 prior to 9/30/16. Keep fingers crossed :)

    -brady
    OEMR Organization

     