Hi Mark,
Thank you for your answers.
I have completed and reformulated the remaining question, see below.
> _ Our experimentation consists in planning motion for several
> objects to manipulate. During the experimentation the start and
> goal poses of the objects will be always the same for each object.
> The data base of Thunder grows at each time the planner from
> scratch (PFS) find a solution before the retreive-repair planner
> (RR). However, when the database contains the path, the PFS has a
> low probability to find a path first and maybe to improve the
> quality of the database in order to have more optimal path for
> future planning request. So, is it possible to force the PFS to
> generate trajectory in order to improve the database?
>
I am a little confused. PFS and RR run in parallel threads.
Whichever finds a solution first will terminate the other thread.
What I mean is, once a path exists (or almost) in the database, the
probability for the PFS thread to return a solution first is lower than
this one for the RR thread. Because a single planning request takes a
lot of time (20-30s) for this problem. Moreover, in this case the
database has a low probability to be enriched and improved.
So it is possible to force the PFS thread to work alone (to focuse on
the learing) some time in order to build a more "optimal" database? If
yes, Is it possible to do this offline?
Thank you again and congratulation to the whole team, OMPL is a nice
library and well documented.
Regards,
Yoann.
On 09/30/2016 06:40 PM, Mark Moll wrote:
> Hi Yoann,
>
> My answers are below inline.
>
> Mark
>
>
>
>> On Sep 28, 2016, at 7:23 AM, Yoann Solana <ys...@la...
>> <mailto:ys...@la...>> wrote:
>>
>> Hi all,
>>
>> We are working on the implementation of research work about dual-arm
>> manipulation.Our goal is to develop in Moveit a new functionality
>> able to execute complex closed kinematics chain motions in a
>> cluttered environment. For now, we are able to plan motion with the
>> RRT planner. However, the workspace is very complex, so that planning
>> requests are almost impossible to solve in a short time (1-2s).
>> Therefore, we want to take advantage of multi-query planners like PRM
>> or SRS to compute offline a roadmap of the workspace in order to
>> efficiently perform a motion request later.
>>
>> In previous posts
>> (https://sourceforge.net/p/ompl/mailman/message/32657097/,
>> https://sourceforge.net/p/ompl/mailman/message/35074389/), Mark Moll
>> explained that is was not possible to restart the planner using
>> a previously constructed roadmap without a lot of work in the code.
>> However, he proposed experienced based planners.
>>
>> I read the article "Experience-Based planning with Sparce Roadmap
>> Spanners" and the LightningThunder demo. I'm thinking about using the
>> Thunder framework inside Moveit, but I need to be sure if it will be
>> in accordance to our requirements.
>> I have several question about the Thunder framework:
>> _ The exp-based planning is suited for robots with large number of
>> invariant constraints. So, for our case, additional constraints
>> generated by closed kinematic chains can be easily encoded in the
>> experience database. This will lead to have a robust database. Am I
>> right?
>>
>
> Yes.
>>
>> _ I see the size of the data base have a kind of theoretical limit.
>> However, can I be sure that the database will have a size limit, even
>> after months of running?
>>
>
> The database is *guaranteed* not to grow indefinitely. This is because
> it is using the spanner properties of the underlying SPARS2-based
> planner. By changing the planner parameters you can control how sparse
> the roadmap (and how large the database) will be. We can’t predict
> what the size of the database will be in the limit, though.
>>
>> _ Our experimentation consists in planning motion for several objects
>> to manipulate. During the experimentation the start and goal poses of
>> the objects will be always the same for each object. The data base of
>> Thunder grows at each time the planner from scratch (PFS) find a
>> solution before the retreive-repair planner (RR). However, when the
>> database contains the path, the PFS has a low probability to find a
>> path first and maybe to improve the quality of the database in order
>> to have more optimal path for future planning request. So, is it
>> possible to force the PFS to generate trajectory in order to improve
>> the database?
>>
>
> I am a little confused. PFS and RR run in parallel threads. Whichever
> finds a solution first will terminate the other thread.
>>
>> _ Last question, I see the experimentation in the article was perform
>> with Moveit/OMPL. Is it possible to have more documentation about the
>> implementation in Moveit?
>>
> That’s a great idea. Dave Coleman (cc-ed) has written most of this
> code. I hope he can find some time to write some instructions on how
> to use Thunder/Lightning with MoveIt!.
>
>
>
|