#211 Baseline Duration/Start/End 2010 MPP missing

open
nobody
None
5
2013-04-03
2013-04-03
Cosmina
No

Hello,
I'm trying to convert a simple mpp created in MSP2010 with actual values for Baseline Duration, Baseline Start, Baseline End but they do not appear in resulting mpx file. I'm attaching the 2 files.
Note: the values seems to be in the fields net.sf.mpxj.TaskField.BASELINE_ESTIMATED_DURATION, net.sf.mpxj.TaskField.BASELINE_ESTIMATED_START, net.sf.mpxj.TaskField.BASELINE_ESTIMATED_START

Discussion

  • Cosmina

    Cosmina - 2013-04-03

    original mpp file

     
  • Cosmina

    Cosmina - 2013-04-03

    resulting mpx file

     