#1475 Monthly sched with duration has problem

v4.0.x
open-fixed
Server (672)
5
2012-05-04
2012-05-03
No

A monthly schedule occurring on day 29,30 or 31 with a duration starting in a month with less days than that (eg occur on 31st starting June 30) doesn't start when expected, instead it rolls over to the next month.

Example:
Day 31 of Every 1 Month
Starting at June 30, 2012 (or any day in June)

Will trigger on
July 1
August 31
etc.

Should be:
June 30
July 31
etc.

Discussion

  • Emanuel Norrbin

    Emanuel Norrbin - 2012-05-04
    • status: open --> open-fixed
     
  • Emanuel Norrbin

    Emanuel Norrbin - 2012-05-04

    This has been fixed in the 4.0.x branch (r52198) and will go into the 4.0.5.17 build.

     
  • Emanuel Norrbin

    Emanuel Norrbin - 2012-05-04

    There is a simple work-around for this problem. Just configure your schedule to start on any day in the first month you want this schedule to trigger.

     
  • Emanuel Norrbin

    Emanuel Norrbin - 2012-05-04

    Actually will go into build 4.0.5.19.