From: Jane J. <jan...@bo...> - 2005-05-19 11:30:01
|
The following is the prioritised schedule for work currently being undertaken for release 2.6 as agreed at the meeting on 29 April: By 21st May: JDK 1.5 (into 2.4.3) Log4J Context Listener Installation and Setup Servlet Improvements Error Ant Static call *Timestamp and major milestone* Versioning scheme document to be edited with agreed strategy Title tag fix Time-out Notifications *Milestone (21st May)* By 7th June: Look and feel MT to test Resource Tree IMS CP Split of templates *By 7th July* Time Release HSQLDB RSS Resource Tree Text/Image Block/Announcement ACL editor HTML widget with <EM> fix MVN Resource Display Superlinks Webauth *Milestone* Resource searching Easybuilder *Milestone (7th July)* Testing Deploy by end of July into whole system. |