From: Marcin H. <gan...@gm...> - 2026-03-02 16:23:55
|
On Mon, 2 Mar 2026 at 16:59, Phil Stracchino <ph...@ca...> wrote: > > The *problem* is that yesterday, *SUNDAY* March 1, the Incrementals that > *should* have run, that run *every* Tuesday through Sunday, didn't. > That's what I'm trying to find an explanation for. Hello Phil, You can test your schedule in bconsole. For example like this: status schedule="Monthly Rotation" time="2026-03-01 00:00:00" Is your missing incremental backup listed there? If it is, then with your Bacula schedule setting is everything fine but it can mean an other problem (or a bug). If it is not listed, then it can mean that something is wrong with the schedule configuration. Best regards, Marcin Haba (gani) |