#94 Task start and finish times are wrong

1.5_beta3
open
nobody
None
7
Linux_Mint_13
Gnone
User_Interface
Blocker
2014-06-19
2014-06-19
No

I have an MS project 2007 file (.mpp). When open in MS project, the start times are different to those in ProjectLibre 1.5.9. There is no consistent offset throughout the file, the times are out by 8 hrs, 16 hrs, 6 days 16 hrs, etc... I have used MPXJ to view the raw data, and the times displayed by ProjectLibre have no relation to the times in the file.

Discussion


Log in to post a comment.