Hello,
I'm just new to Openproj but liking it very much so far.
I have 1 thing I can't find though.
I have a resource that works 50%, now when I assign him to a task that takes 1day of work, the work should be spread over 2 days. How can I achieve this?
I expected the resource availability to handle this, but it doesn't seem to work.
I know I can give the % when assigning a resource to a task, but I'd prefer not to do this for every task he has.
thanks!
Meutte
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Hello,
I'm just new to Openproj but liking it very much so far.
I have 1 thing I can't find though.
I have a resource that works 50%, now when I assign him to a task that takes 1day of work, the work should be spread over 2 days. How can I achieve this?
I expected the resource availability to handle this, but it doesn't seem to work.
I know I can give the % when assigning a resource to a task, but I'd prefer not to do this for every task he has.
thanks!
Meutte