meutte - 2010-04-15

Hello,
I'm just new to Openproj but liking it very much so far.
I have 1 thing I can't find though.
I have a resource that works 50%, now when I assign him to a task that takes 1day of work, the work should be spread over 2 days. How can I achieve this?

I expected the resource availability to handle this, but it doesn't seem to work.
I know I can give the % when assigning a resource to a task, but I'd prefer not to do this for every task he has.

thanks!
Meutte