#375 MRP does not consider components wastage Quantity in Demand

open
MRP (51)
5
2012-05-27
2012-05-27
No

Hello Victor
I have noticed that MRP does not bring the component quantity issued as wastage in the Demand.
In order & receipts window I entered quantity of a component in the wastage column, which is next to 'qty to deliver column. In the next MRP, system should bring this wastage as Demand for its parent MO. But this is not happening. I can see that the scrap field is updated in the MO component

The attached screen images shows an example

Kindly look into this matter

Thanks
Johnson

Discussion

  • Johnson Joseph

    Johnson Joseph - 2012-05-27
    • assigned_to: nobody --> vpj-cd
     
  • Johnson Joseph

    Johnson Joseph - 2012-05-27
     
  • Johnson Joseph

    Johnson Joseph - 2012-05-27
     
  • Johnson Joseph

    Johnson Joseph - 2012-05-27
     
  • Johnson Joseph

    Johnson Joseph - 2012-05-27
     