    Now, expired item is changed the icon into warning icon automatically. Could you change this format? Please keep its icon as end user seeting but strike through the text. Sometime expired items are still kept as history reference. If we change the icon, it is hard for end user. Thanks & Best regards

  • Phuoc Huu Nguyen Phuoc Huu Nguyen posted a comment on discussion General Discussion

    Oh, I found that in default it is in my expectation, why in my project which has many tasks, it isn't

  • Phuoc Huu Nguyen Phuoc Huu Nguyen posted a comment on discussion General Discussion

    Dear All, I am using ProjectLibre 1.8. I have task T1, T2. T2 is dependent on T1 with type FS. T1 is 6 hour task. T2 is 4 hour task. I am expecting T2 start in the date when T1 finish. Actually T2 is started in the next day. Could I achive my expectation? Thanks you very much for your help