Release 1.4.8 (2011-10-23):

  o Strongly enhanced the upgrade mechanism. Now it's more robust, should work with all the databases and between arbitrary Test Manager versions.

    The only drawback is that upgrade is only supported from 1.4.7, not from previous versions.

  o Enhancement #9077 (Track-Hacks): Ability to separate and report on test plans by product

  o Enhancement #9208 (Track-Hacks): Test plan with only selected test cases from the catalog, take snapshot version of test cases.
                                     This is an important one. Many users were asking for a way of including only selected test cases into
                                     a Test Plan, for different reasons. Now you have it :D

  o Added ability to search through the test plans of a catalog.

  o Added French language catalog! Thanks to someone who doesn't want to be cited :D

  o Fixed Ticket #9141 (Track-Hacks): Update installation 1.4.6 -> 1.4.7 not possible
  o Fixed Ticket #9167 (Track-Hacks): installation of 1.4.7 with postgres database not possible
  o Fixed Ticket #9187 (Track-Hacks): Current test status report should consider only last result of a testcase in the plan.
                                      Thanks to Andreas for his contribution to fixing this one!

Thanks to everyone who contributed with ideas, testing and language translations!!!

Enjoy!
Roberto