From: Andreas K. <and...@ac...> - 2009-10-27 15:45:46
|
Larry W. Virden wrote: > On Mon, Oct 26, 2009 at 6:48 PM, Andreas Kupries > <and...@ac...> wrote: > >> Based on these dates my proposal >> >> Mo Nov 9 4 weeks Testing, CVS bugfix commits, writing up release >> notes, fixing version numbers. >> Mo Dec 7 1 week RC available for general testing, CVS frozen >> Mo Dec 14 Release >> > Should one of the goals be to run the test suite against the current > CVS head for Tcl 8.5 and 8.6, to verify the various modules are > working against the current release as well as the impending release? Yes. While the 8.6 branch is technically still in beta it should be really near to its final form by now. -- Sincerely, Andreas Kupries <an...@ac...> Developer @ <http://www.activestate.com/> |