From: Andreas K. <and...@ac...> - 2008-11-25 18:06:09
|
As seen from the version number, I consider this aminor release, mainly to get Alejandro Paz's graph operations (his GSoc work for us) into a release. We got some other small stuff as well. Anybody else having things to add ? Now is the time. Current planning ** Do the main release work next week. ** Create a release candidate (RC) during the weekend after (Dec 6-7). ** Put the RC up next Monday (Dec 8) and let it up for a week. ** Convert the RC to release on Dec 15, pending major changes. This gives this and next week for the release work, and another week with the RC out for general testing. Time constraint: I am leaving for Xmas vacation on Monday Dec 23. The release date is one week before that to keep these dates nicely apart. Is someone willing to step up and do a Tklib release as ell ? -- Andreas Kupries <and...@Ac...> Developer @ http://www.ActiveState.com Tel: +1 778-786-1122 |