Select "Export only the selected items" unless you want all tasks
Select "Put dates and times in separate columns" then press OK
Choose a name and save the file somewhere you can find it (e.g. Desktop)
From Outlook:
Select the Tasks panel
Select "File: Import and Export"
Select "Import from another program or file" and press Next
Select "Comma Separated Values (Windows)" and press Next
Browse to the file you saved and select it
Choose the options you prefer (Replace duplicates, allow or do not import) and press Next
Leave default "Select destination folder:" to Tasks and press Next
Press "Map custom fields"
Drag and drop fields from your Task Coach CVS file from the left to the Outlook to the right and ensure that on the right the "Fields" and "Mapped" from are as follows:
Subject mapped from Subject
Start date mapped from Actual start date
Due date mapped from Due date
Reminder On/Off unmapped
Reminder date mapped from Reminder date
Reminder time mapped from Reminder time
Date Completed mapped from Completion Date
% Completed mapped from % Complete
Total work unmapped
Actual work mapped to Time Spent (this is calculated from the Effort on Task Coach)
Billing information mapped from Revenue if you want
Categories mapped from Categories
Notes mapped from Description
Priority mapped from Priority
Press OK then Finish
Double click the task/s you have imported and change the following:
select the Reminder checkbox (if you have reminders! Although you have set reminders, outlook works like an alarm clock that you need to turn it on as well)
Press Details on the taskbar and change the Actual work to hours (Outlook confuses Hours for Minutes)