Menu

#16 Quality Assurance Plan

Task
open
None
2015-05-16
2015-05-10
No

Discussion

  • Zubir Rentiya

    Zubir Rentiya - 2015-05-11

    completed chapter 1 of plan Now working on chapter 2.

     
  • Zubir Rentiya

    Zubir Rentiya - 2015-05-16

    completed chapter 2 of plan. Now working on 3.

     
  • Zubir Rentiya

    Zubir Rentiya - 2015-05-16

    Completed Section 3 of plan. Now working on 4

     
  • Zubir Rentiya

    Zubir Rentiya - 2015-05-16

    Completed section 4. Now working on section 5.

     