Again a nice version! Thanks! I've updated to v1.39 and worked OK but I noticed some differences.
When I switch to the project-view (projects left), in the old version the Name of the persons were shown in the table.
In the new version, the USERID is shown.
Is it possible to change to the Name?
A second question: Is it possible to activate a template where the weekend is gray like in the older version?
Thanks!
Waldo
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Hi, I managed to get the weekends back in gray.
-In parameters: uncheck the weekend days
-Activate the option Display tasks overlapping weeknds and days off
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
View and moderate all "Help" comments posted by this user
Mark all as spam, and block user from posting to "Discussion"
Hi,
Again a nice version! Thanks! I've updated to v1.39 and worked OK but I noticed some differences.
When I switch to the project-view (projects left), in the old version the Name of the persons were shown in the table.
In the new version, the USERID is shown.
Is it possible to change to the Name?
A second question: Is it possible to activate a template where the weekend is gray like in the older version?
Thanks!
Waldo
View and moderate all "Help" comments posted by this user
Mark all as spam, and block user from posting to "Discussion"
Hi, I managed to get the weekends back in gray.
-In parameters: uncheck the weekend days
-Activate the option Display tasks overlapping weeknds and days off