#51 Change request

open
None
7
2011-07-29
2009-08-21
M. Günter
No

A CR is a special kind of requirement: it is "later" in the process. It invalidates, updates, changes other requirements.
The CR list should be viewable. The acceptance process for a CR is usually more elaborate.

Explicite acceptance is required.

The new status must be: depended requirements updated.

A CR has a list of requirements it influences.
The list must be editable

Discussion

  • M. Günter

    M. Günter - 2009-08-21

    The change also contains a reason for the change. And a cost estimate.
    Otherwise it is a "normal" requirement.

     
  • M. Günter

    M. Günter - 2011-04-28
    • priority: 5 --> 7
     
  • Slav Peev

    Slav Peev - 2011-07-29
    • assigned_to: nobody --> slavpeev