From: Bill H. <bi...@lo...> - 2003-11-04 15:13:42
|
After a lot of thought, here's the schedule I propose: 5-Nov: 0.8.2 is released CGLIB-2 branch is created 7-Nov: 0.8.2-cglib-2-b1 is released (from CGLIB-2 branch but with patch for cglib 2 and new Enhancer API) 20-Nov: 0.9.0 release process starts (beta, then release candidates) 27-Nov: 0.9.0 final Note 1. Depending on release schedule of CGLIB 2 and feedback from the Hibernate team the CGLIB-2 branch may or may not be included in 0.9.0. Note 2. If Hibernate looks like it will release 2.1 final before 0.9.0 then we will release 0.8.3 in time to be included in their release. This will include the cglib-2 patch, but not the DataSource stuff. Note 3. The reason why we are producing a beta release of Proxool with cglib-2 support before cglib-2 is finally released is that Hibernate want to include cglib-2 in their beta releases of 2.1. And Hibernate have a dependency on Proxool (we are one of their bundled JDBC pools). Bill |