#86 Can't mark a task complete if work off in the middle

1.5.2
open
nobody
None
6
Red_Hat_Enterprise_Linux_6
Gnone
Scheduling
Major
2014-04-10
2014-04-10
Eric L.
No

Hello,

steps to reproduce issue:

  • create a task of e.g. 4 days
  • assign a resource to this task
  • edit the calendar of this resource to set the 3rd day as holiday, i.e. the 3rd and 4th day are delayed by 1 day.
  • try to set the task to 100% completion
  • you can't, it gets stuck at 50%

Cheers, Eric