Hi everyone. I am trying to duplicate a project only copying the structures, duration, predecessors and names.
Basically, I just want to copy-paste the following columns:
1. Parent ID (Just to transfer the structure to the project, if there is a better way, I am open to hearing it)
2. Name
3. Duration
4. Predecessors
I've tried copy-pasting this 4 columns, but predecessors are not transfering correctly, and Parend ID does not change when I paste.
Any help is appreciated!
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Hi Gregorio, there has been a limit to cut/paste in the current spreadsheet. i think it will take a complete rip and replace of the spreasheet library to a new one to fix. We re-wrote entirely the Cloud verson and the spreadsheet we are using correctly cut/paste.
Last edit: Tahoeob 2024-09-19
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Hi everyone. I am trying to duplicate a project only copying the structures, duration, predecessors and names.
Basically, I just want to copy-paste the following columns:
1. Parent ID (Just to transfer the structure to the project, if there is a better way, I am open to hearing it)
2. Name
3. Duration
4. Predecessors
I've tried copy-pasting this 4 columns, but predecessors are not transfering correctly, and Parend ID does not change when I paste.
Any help is appreciated!
Hi Gregorio, there has been a limit to cut/paste in the current spreadsheet. i think it will take a complete rip and replace of the spreasheet library to a new one to fix. We re-wrote entirely the Cloud verson and the spreadsheet we are using correctly cut/paste.
Last edit: Tahoeob 2024-09-19