    Hi, I'm trying to set up a project plan with each of my resources only available for 4 hours / week or 10% of the week.

    If a task is estimated to take 12 hours, I would like to see the start and end date to be approximately 3 weeks apart.

    Could someone provide me with a little guideance?

    Regards,

    Jim P.

     
  • Jacob Joel

    Jacob Joel - 2016-04-21

    Can Project Libre file be converted to csv or excel file?

     
    • J Ruedinger

      J Ruedinger - 2016-05-08

      Mark the lines you want to export, copy and paste to Excel.

       