Hi, I'm trying to set up a project plan with each of my resources only available for 4 hours / week or 10% of the week.
If a task is estimated to take 12 hours, I would like to see the start and end date to be approximately 3 weeks apart.
Could someone provide me with a little guideance?
Regards,
Jim P.
Can Project Libre file be converted to csv or excel file?
Mark the lines you want to export, copy and paste to Excel.