Contingency reserve

2022-02-13
2022-02-13
  • Attila Szuts

    Attila Szuts - 2022-02-13

    Hello, I'm just learning project management and ProjectLibre is an amazing tool! I've created Tasks (WBS), Resources with costs.
    Is there any solution to add Contingency reserve to my budget plan?
    May I add some "Material" resource named as "Contingency reserve" and assign it to milestones or the whole project?
    (other but similar question is Management reserve)
    Or I have to add a "Contingency reserve" activity (task) that has a duration nearly as long as my whole project and assign budget to this task?

    thanks

     
  • Tahoeob

    Tahoeob - 2022-02-13

    That is a superb question for someone just learning project management! There are a couple ways to do this and just brainstorming here are a few:

    • Create a resource contingency and give a cost
    • Create the resource either with 100% Max Units or a smaller number.... or when assigning to a task use 100% or less. It will create that resulting cost on the project

    Now.... you can use the Task Usage spreadsheet to alter the costing/assignments on tasks or create the dummy task with duration/assignment combination to create the cost buffer you are looking to create.

    Or: you can create a Project Summary task that spans the entire project. If you assign a resource to that Summary task it will give an error and an icon to the far left noting you have assigned a resource to a Summary task. It is not good practice for pure PM management but for using to create a buffer seems like a reasonable solution. It will roll up your Costs and Baseline costs correctly in the WBS for instance.....

    That was brainstorming on a Sunday so perhaps better answers.

     
    👍