Hello.
I have multiple resources (worker) and some tasks (all ASAP without any start or end-date).
When I choose "File" and click "update" so that LibreProj reorder all tasks, then it shall put one task after the other (any order accepted).
LibreProj keeps all tasks at the same days so that many of my resources are taken 20h instead of 8h.
How do you limit the daily use of resources and make LibreProj order the tasks in a way, that no resource will have to do overtime?
Cheers!
Mike
Hello, I'm experiencing the same problem. Did you get an answer or find a solution?
Sean
Log in to post a comment.
Hello.
I have multiple resources (worker) and some tasks (all ASAP without any start or end-date).
When I choose "File"
and click "update" so that LibreProj reorder all tasks,
then it shall put one task after the other (any order accepted).
LibreProj keeps all tasks at the same days so that many of my resources are taken 20h instead of 8h.
How do you limit the daily use of resources and make LibreProj order the tasks in a way, that no resource will have to do overtime?
Cheers!
Mike
Hello, I'm experiencing the same problem. Did you get an answer or find a solution?
Sean