How can I adjust the default working hours for the standard calendar (not on a per-day basis)?
Also, when in the Resource Usage view I see tasks (by default) have 8h per day. I have adjusted the Hours per day (within the Duration Settings dialog) to 7.5 hours - why is this not reflected in the Resource Usage view?
Thanks in advance - Joel.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Bumping this question, as it's exactly what I'm trying to find out! My stores are open 9am-9pm 7 days a week, so the default 8am-5pm Mon-Fri doesn't suit any of my staff's schedules.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
How can I adjust the default working hours for the standard calendar (not on a per-day basis)?
Also, when in the Resource Usage view I see tasks (by default) have 8h per day. I have adjusted the Hours per day (within the Duration Settings dialog) to 7.5 hours - why is this not reflected in the Resource Usage view?
Thanks in advance - Joel.
Bumping this question, as it's exactly what I'm trying to find out! My stores are open 9am-9pm 7 days a week, so the default 8am-5pm Mon-Fri doesn't suit any of my staff's schedules.