Dear All,
I am using ProjectLibre 1.8. I have task T1, T2. T2 is dependent on T1 with type FS. T1 is 6 hour task. T2 is 4 hour task. I am expecting T2 start in the date when T1 finish. Actually T2 is started in the next day. Could I achive my expectation? Thanks you very much for your help
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
I noticed various problems with task dependencies as well. I'm using backward planning, and every time I add a dependency it does not what I expet it do do. EE dependencies are not working at all.
Dont know if this is a PL 1.8 issue, but this release is very buggy. I'm thinking of going back to 1.7
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Dear All,
I am using ProjectLibre 1.8. I have task T1, T2. T2 is dependent on T1 with type FS. T1 is 6 hour task. T2 is 4 hour task. I am expecting T2 start in the date when T1 finish. Actually T2 is started in the next day. Could I achive my expectation? Thanks you very much for your help
Oh, I found that in default it is in my expectation, why in my project which has many tasks, it isn't
I noticed various problems with task dependencies as well. I'm using backward planning, and every time I add a dependency it does not what I expet it do do. EE dependencies are not working at all.
Dont know if this is a PL 1.8 issue, but this release is very buggy. I'm thinking of going back to 1.7