Gantt Chart changes everytime open a saved file

Bug List
Anonymous
2022-05-21
2022-09-09
  • Anonymous

    Anonymous - 2022-05-21
    Post awaiting moderation.
    • Tahoeob

      Tahoeob - 2022-05-21

      You are anonymous which makes it dificult... are you cutting/pasting tasks ?

       
    • Tahoeob

      Tahoeob - 2022-09-09

      I took a look at this again and baselined your project, then I closed and re-opened the project. The schedule was the same as the baselined project. I am not sure what is different with your version but this seemed fine.

       
  • Anonymous

    Anonymous - 2022-06-08
    Post awaiting moderation.
    • Tahoeob

      Tahoeob - 2022-09-09

      That is strange.... I tried again and opened the project. There is no RBS as none of the resources are indented which creates the RBS structure (or WBS for tasks).... I randomly indented a few resources and then saved... closed...re-opened and the RBS was still there acccurately. The resources also opened as Material resources. What is your computer configuration?

       