Task templates

Help
2012-02-14
2012-12-15
  • Iosif Koidis

    Iosif Koidis - 2012-02-14

    Hi i would like to know if there is a way to make something as a template for tasks. My problem is that i have tasks that are different but have the same subtasks. Is there a way to do that?

    Thank you in advance

    Iosif

     
  • Kai Reinhard

    Kai Reinhard - 2012-02-27

    No, not yet. May-be a clone functionality for tasks could be useful or favorites.

     
  • Kai Reinhard

    Kai Reinhard - 2012-02-27

    We discussed this issue here earlier, but we've no idea on how to deal with.

     
  • ebeke

    ebeke - 2012-05-14

    Hello Kai,

    A task cloning feature would be incredibly useful for me as well, given I have a similar work practice as Losif.

    For task cloning to work you would have to as a user write the subtasks fairly non specific to the root/parent task such that you would only have to change the root/parent task title.

    Perhaps when you perform a task cloning operation it could bring up an array of cells with each task subtask hierarchy displayed in it allowing you to either clear the cells relating to scheduling/gant/precedence or enter/select new values, espcecially dates.

    As a usage example, i would like to create a task with the same task hierarchy comprised of the same tasks but change the name of the top level task and dates of the remaining tasks within the hierarchy.

    Regards,