#66 Product based planning (Prince2)

open
nobody
None
5
2009-10-09
2009-10-09
pieter
No

Product based planning (standard practice within Prince2) would be an interesting feature for the next release.
It is possible to use the WBS and substitute Products for Work. But then you are still missing:
- visual product trees
- product flow diagrams
- stage planning.

As an added incentive: I was told Microsoft is developing this feature for a next release.