Open Workbench ressources

2013-12-18
2013-12-23
  • Karsten Iversen

    Karsten Iversen - 2013-12-18

    I have a project with delievery before a certain day, this I have set in the proberties for the specific task, but when calculation is done the task is moved later than the finish before date?

    Another issue is with ressources and calculation times. If I have a project with a fixed time on 10d and put a labor on the task, then the labor doesn´t have time registret in the unused timeoverview. Should there be anything registret in the estimated time at the task?

     
    • martink

      martink - 2013-12-23

      As you can see this place is not very active. You could try
      http://workbenchwarrior.wordpress.com/
      or
      CA Clarity Global user community OWB message board.
      Which version of OWB is that?
      So you have set the must finish constraint?
      Is there an option in the autoschedule to honor the constraints.

      When you assign a resource to a task there is no ETC assigned automatically.
      You have to set the ETC manually.

       

Log in to post a comment.