I have imported a project file from MS Project 2003 (exported in XML format and imported in OWB) and for some reason I ignore, I cannot set the task status to "completed" although the task has "%Complete = 100%"
Logged In: YES user_id=1356873
Is %Complete = 100% user enter value or % Expended? Is there remaining ETC for the task
Log in to post a comment.
Logged In: YES
user_id=1356873
Is %Complete = 100% user enter value or % Expended?
Is there remaining ETC for the task