#57 Task's successor is postponed to next day

v1.1_RC3
open
nobody
Project (26)
5
2005-09-19
2005-09-19
Anonymous
No

When a task is less than a day (like a meeting), even
if it takes only one hour and start at the beginning of
the day, it's successor(s) will only start the next
day. A work-around (cheat) is to set the successor
with a lag of –1 day.

I perceive this as is a major bug since it corrupts the
logic and duration of most projects.