How to apply non-working days - v1.4

Help
2011-09-07
2013-05-15
  • canadairman

    canadairman - 2011-09-07

    Hi,
    I have creating the planning of a project with a Standard calendar.
    Then I created a custom calendar with some non-working days.
    I checked that the ressources are using this custom calendar.
    But i don't see any change on the planning of the project. Even if a ressource is not working, the task finishs at the same time.

    Am I missing something ?
    Thanks

     
  • HAMF

    HAMF - 2011-10-04

    Hello there.
    I have done almost the same, but applying the non-working days on the standard calendar.
    It worked ok.
    It is always an alternative.
    HF

     
  • Anonymous - 2012-10-16

    Just to complete, I have the same issue.  And apply it to standard calendard affect all ressources, right ???  If so, that mean every resource go in vacation at the same time : ouchhhh!

     