Chestire - 2013-04-07

Running: latest version on March 2013, Mac OS X

As with many applications using Microsoft DBs, registering changes implies each interaction is confirmed before taking effect.

Please select weekdays on Calendar (press weekday name), change working h  (select non-standard calendar) and click ok: it must be done for each workday, that is, change Monday, click OK, change Tuesday, click OK, …

Notice if there is the need to change several days, for the changes to take effect, each change must be confirmed with OK before OpenProj can process the next change.