How to control timescale on OpenProj?

Help
pwjone1
2009-12-05
2013-05-15
  • pwjone1

    pwjone1 - 2009-12-05

    Apologies if this shows up twice, but I posted once, cannot see it, so trying again.

    I'm having some trouble with the way timescales are managed in OpenProj v1.4.  I'm working in a higher time scale, quarters and years.  I can get there via magnify (repeatedly), but I have two problems:

    1. The time scale does not seem to be saved with the file.  When I re-open it, it shows up as the old days sort of thing.  Is that a bug?
    2. I really don't care about hours, but cannot seem to find a way to drop that from the start/stop type entry fields.  Any way to make that go away?

    Thanks.

     
  • pwjone1

    pwjone1 - 2009-12-05

    I guess I should note that I know to hit the magnify plus button a bunch of times, to get the timescale back up to quarters/years. but really I was hoping to just not have to do that every time I go back into a file.  MSPROJ obviously enough doesn't behave this way.

     