diana - 2013-02-21

In openproj , I have a task that is worked on by 3 resources. Originally in the beginning , I assigned 36 hours for the "Work" field in the "General" tab in the Task Information dialog box , so 12 hours for each resource. But then now , I am where i am filling in the % completion of each task and each resource finished the task but only spent 8 hours each instead of 12 hours , how do I  record that ? Where do I write that new "8 hours " ?